Kemerton processing plant internal roads

user icon green
CLIENT
HIWAYS
clock icon green
DURATION
3 weeks
calendar icon green
YEAR
2026
location marker icon green
LOCATION
Kemerton
The Project
  • Comprehensive site traffic management
  • Phased project delivery in collaboration with key site personnel
  • Pothole rehabilitation through scarifying, conditioning, and recompacting existing pavement
  • Removal and replacement of unsuitable in-situ materials with basecourse material
  • Final trimming and water-binding the road surface to achieve the correct texture for sealing
  • Construction of a new light vehicle car park
Deliverables
  • 7 skilled plant operators + 1 experienced construction supervisor
  • Grader
  • 6×4 Water Truck & 6×4 Tipper
  • Skid Steer
  • Smooth Drum Roller & Multi-Tyre Roller
  • Front End Loader
Achieved Results

Zero operational disruptions and high safety standards maintained throughout — full mine-site operations continued uninterrupted while the roadworks package was delivered to program.